Prisma
P51800004199
Delivered on time
Marked completed on the registry on or before the promised deadline.
Where this project stands
The journey from RERA registration to completion, in order.
Completed.
Registered with RERA
8 Aug 2017Original promised completion
30 Jun 2018The deadline the builder committed to at registration.
Marked completed on the portal
Shown as completed on the official registry (no exact date scraped).
Timeline & delay
Key dates and how they compare to what was promised.
8 Aug 2017
When the project was registered with RERA.
30 Jun 2018
The deadline committed to at registration.
30 Jun 2018
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
15
Complaints against the builder
0
Often reported per project on MahaRERA
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 10 months.
Official records
Builder: Oberoi Constructions Limited (NAME:Oberoi Constructions Limited)
Data last refreshed 21 Jun 2026.