OCEAN STAR II
P51900007777
Behind schedule
This project is about 82 months past its latest deadline and is not yet marked completed.
Where this project stands
The journey from RERA registration to completion, in order.
Past deadline by ~82 months.
Registered with RERA
18 Aug 2017Original promised completion
31 Aug 2018The deadline the builder committed to at registration.
Revised deadline after extensions
31 Aug 2019Pushed back ~12 months across 1 extension.
Today — still not completed
About 82 months past the latest deadline.
Timeline & delay
Key dates and how they compare to what was promised.
18 Aug 2017
When the project was registered with RERA.
31 Aug 2018
The deadline committed to at registration.
31 Aug 2019
After all approved extensions.
—
Handover date, when available.
82 mo overdue81.7 mo
How far past deadline an ongoing project is.
1
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
0
Complaints against the builder
0
Often reported per project on MahaRERA
No complaints found in the data we have. This isn't a guarantee — verify on the portal.
Extension history
Each time the completion deadline was officially pushed back.
| From | Extended to | Reason |
|---|---|---|
| 31 Aug 2018 | 31 Aug 2019 | MahaRERA extension (original vs revised completion date) |
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 13 projects — 4 delivered, 9 still active. 8 of 13 (62%) ran late by an average of 15 months.
Official records
Builder: SURAJ ESTATE DEVELOPERS LTD (NAME:SURAJ ESTATE DEVELOPERS LTD)
Data last refreshed 21 Jun 2026.