SURAJ ESTATE DEVELOPERS LTD
RERA delivery track record · complaints · project delays
NAME:SURAJ ESTATE DEVELOPERS
F3/100
Poor track record
Tracking 13 projects — 4 delivered, 9 still active. 8 of 13 (62%) ran late by an average of 15 months.
Delivery breakdown
How this builder's 13 tracked projects are split by outcome.
Key numbers
Total projects
13
Active
9
Completed
4
Delayed
8 (62%)
Late or overdue
Avg delay
15 mo
Worst: 18 mo
On-time rate
0%
Of completed projects
Extension rate
77%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (13)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
P51900004549 Mumbai City · MH | Mumbai City MH | 9 Aug 2017 | 31 Dec 2018 | Completed | 12 mo delay |
P51900004642 Mumbai City · MH | Mumbai City MH | 9 Aug 2017 | 31 Mar 2019 | Completed | 18 mo delay |
P51900005428 Mumbai City · MH | Mumbai City MH | 11 Aug 2017 | 30 Jun 2019 | Completed | 18 mo delay |
P51900007257 Mumbai City · MH | Mumbai City MH | 17 Aug 2017 | 30 Jun 2023 | In progress | On track |
P51900007777 Mumbai City · MH | Mumbai City MH | 18 Aug 2017 | 31 Aug 2018 | Overdue | 82 mo overdue |
P51900003689 Mumbai City · MH | Mumbai City MH | 6 Aug 2017 | 31 Dec 2018 | Completed | 12 mo delay |
P51900010078 Mumbai City · MH | Mumbai City MH | 23 Aug 2017 | 30 Jun 2022 | Overdue | 48 mo overdue |
P51900008207 Mumbai City · MH | Mumbai City MH | 18 Aug 2017 | 30 Jun 2023 | In progress | On track |
P51900047891 Mumbai City · MH | Mumbai City MH | 1 Dec 2022 | 31 Dec 2026 | In progress | On track |
P51900021953 Mumbai City · MH | Mumbai City MH | 25 Aug 2019 | 30 Dec 2024 | Overdue | 18 mo overdue |
P51900021954 Mumbai City · MH | Mumbai City MH | 25 Aug 2019 | 30 Dec 2024 | Overdue | 18 mo overdue |
P51900031447 Mumbai City · MH | Mumbai City MH | 23 Oct 2021 | 31 Dec 2026 | In progress | On track |
P51900032173 Mumbai City · MH | Mumbai City MH | 14 Dec 2021 | 31 Dec 2026 | In progress | On track |