SURAJ ESTATE DEVELOPERS LTD

RERA delivery track record · complaints · project delays

NAME:SURAJ ESTATE DEVELOPERS

Poor track record

Tracking 13 projects — 4 delivered, 9 still active. 8 of 13 (62%) ran late by an average of 15 months.

Delivery breakdown

How this builder's 13 tracked projects are split by outcome.

4 Delivered late4 Overdue5 In progress

Key numbers

Total projects

13

Active

9

Completed

4

Delayed

8 (62%)

Late or overdue

Avg delay

15 mo

Worst: 18 mo

On-time rate

0%

Of completed projects

Extension rate

77%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (13)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
P51900004549
Mumbai City · MH
Mumbai City
MH
9 Aug 201731 Dec 2018Completed12 mo delay
P51900004642
Mumbai City · MH
Mumbai City
MH
9 Aug 201731 Mar 2019Completed18 mo delay
P51900005428
Mumbai City · MH
Mumbai City
MH
11 Aug 201730 Jun 2019Completed18 mo delay
P51900007257
Mumbai City · MH
Mumbai City
MH
17 Aug 201730 Jun 2023In progressOn track
P51900007777
Mumbai City · MH
Mumbai City
MH
18 Aug 201731 Aug 2018Overdue82 mo overdue
P51900003689
Mumbai City · MH
Mumbai City
MH
6 Aug 201731 Dec 2018Completed12 mo delay
P51900010078
Mumbai City · MH
Mumbai City
MH
23 Aug 201730 Jun 2022Overdue48 mo overdue
P51900008207
Mumbai City · MH
Mumbai City
MH
18 Aug 201730 Jun 2023In progressOn track
P51900047891
Mumbai City · MH
Mumbai City
MH
1 Dec 202231 Dec 2026In progressOn track
P51900021953
Mumbai City · MH
Mumbai City
MH
25 Aug 201930 Dec 2024Overdue18 mo overdue
P51900021954
Mumbai City · MH
Mumbai City
MH
25 Aug 201930 Dec 2024Overdue18 mo overdue
P51900031447
Mumbai City · MH
Mumbai City
MH
23 Oct 202131 Dec 2026In progressOn track
P51900032173
Mumbai City · MH
Mumbai City
MH
14 Dec 202131 Dec 2026In progressOn track