SURAJ PARK VIEW 2
P51900047891
Under construction
Currently within its planned build window. Watch the deadline and any new extensions.
Where this project stands
The journey from RERA registration to completion, in order.
Approaching the deadline.
Registered with RERA
1 Dec 2022Original promised completion
31 Dec 2026The deadline the builder committed to at registration.
Today — in progress
About 6 months left until the deadline.
Timeline & delay
Key dates and how they compare to what was promised.
1 Dec 2022
When the project was registered with RERA.
31 Dec 2026
The deadline committed to at registration.
31 Dec 2026
After all approved extensions.
—
Handover date, when available.
On track0 mo
How far past deadline an ongoing project is.
0
More extensions can signal execution risk.
Complaints
Buyer complaints recorded on the official registry.
Complaints on this project
1
Complaints against the builder
0
Often reported per project on MahaRERA
About the builder
How this developer has performed across all their tracked projects.
Poor track record
Tracking 13 projects — 4 delivered, 9 still active. 8 of 13 (62%) ran late by an average of 15 months.
Official records
Builder: SURAJ ESTATE DEVELOPERS LTD (NAME:SURAJ ESTATE DEVELOPERS LTD)
Data last refreshed 21 Jun 2026.