MACROTECH DEVELOPERS LIMITED

NAME:MACROTECH DEVELOPERS LIMITED

Good track record

Tracking 5 projects — 5 delivered, 0 still active. 1 of 5 (20%) ran late by an average of 3 months.

Delivery breakdown

How this builder's 5 tracked projects are split by outcome.

4 Delivered on time1 Delivered late

Key numbers

Total projects

5

Active

0

Completed

5

Delayed

1 (20%)

Late or overdue

Avg delay

3.4 mo

Worst: 16.9 mo

On-time rate

80%

Of completed projects

Extension rate

20%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (5)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
LODHA SEAVIEW
P51900010326
Mumbai City
MH
24 Aug 201730 Dec 2022CompletedOn track
Lodha Parel Project
P51900014910
Mumbai City
MH
11 Jan 201830 Oct 2023CompletedOn track
THE WORLD TOWERS - WORLD ONE - TIER III AND TRINITY
P51900008962
Mumbai City
MH
19 Aug 201730 Jun 2021CompletedOn track
THE WORLD TOWERS - WORLD ONE - TIER II
P51900008345
Mumbai City
MH
18 Aug 201730 Sept 2018Completed17 mo delay
One Lodha Place
P51900014984
Mumbai City
MH
15 Jan 201830 Mar 2023CompletedOn track