MACROTECH DEVELOPERS LIMITED
NAME:MACROTECH DEVELOPERS LIMITED
B75/100
Good track record
Tracking 5 projects — 5 delivered, 0 still active. 1 of 5 (20%) ran late by an average of 3 months.
Delivery breakdown
How this builder's 5 tracked projects are split by outcome.
Key numbers
Total projects
5
Active
0
Completed
5
Delayed
1 (20%)
Late or overdue
Avg delay
3.4 mo
Worst: 16.9 mo
On-time rate
80%
Of completed projects
Extension rate
20%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (5)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| LODHA SEAVIEW P51900010326 | Mumbai City MH | 24 Aug 2017 | 30 Dec 2022 | Completed | On track |
| Lodha Parel Project P51900014910 | Mumbai City MH | 11 Jan 2018 | 30 Oct 2023 | Completed | On track |
| THE WORLD TOWERS - WORLD ONE - TIER III AND TRINITY P51900008962 | Mumbai City MH | 19 Aug 2017 | 30 Jun 2021 | Completed | On track |
| THE WORLD TOWERS - WORLD ONE - TIER II P51900008345 | Mumbai City MH | 18 Aug 2017 | 30 Sept 2018 | Completed | 17 mo delay |
| One Lodha Place P51900014984 | Mumbai City MH | 15 Jan 2018 | 30 Mar 2023 | Completed | On track |