Oberoi Constructions Limited

NAME:Oberoi Constructions Limited

Poor track record

Tracking 3 projects — 2 delivered, 1 still active. 2 of 3 (67%) ran late by an average of 10 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

1 Delivered on time1 Delivered late1 Overdue

Key numbers

Total projects

3

Active

1

Completed

2

Delayed

2 (67%)

Late or overdue

Avg delay

9.5 mo

Worst: 19.1 mo

On-time rate

50%

Of completed projects

Extension rate

67%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
Prisma
P51800004199
Mumbai Suburban
MH
8 Aug 201730 Jun 2018CompletedOn track
Enigma Towers A and B
P51800002656
Mumbai Suburban
MH
2 Aug 201730 Dec 2022Completed19 mo delay
Eternia Towers A to D
P51800006141
Mumbai Suburban
MH
14 Aug 201730 Dec 2022Overdue1 mo overdue