PKS BUILDMART PRIVATE LIMITED

NAME:PKS BUILDMART PRIVATE LIMITED

Poor track record

Tracking 3 projects — 1 delivered, 2 still active. 2 of 3 (67%) ran late by an average of 18 months.

Delivery breakdown

How this builder's 3 tracked projects are split by outcome.

1 Delivered late1 Overdue1 In progress

Key numbers

Total projects

3

Active

2

Completed

1

Delayed

2 (67%)

Late or overdue

Avg delay

18 mo

Worst: 18 mo

On-time rate

0%

Of completed projects

Extension rate

100%

Projects with ≥1 extension

Complaints

0

On the registry

All projects (3)

Every registration we track for this builder. Click any project for the full timeline.

ProjectLocationRegisteredPromised completionStatusDelay
TOWN CENTRAL - PHASE-I
UPRERAPRJ7066
UP
31 Jul 201715 Aug 2022Completed18 mo delay
TOWN CENTRAL - PHASE-II
UPRERAPRJ7355
Gautam Buddha Nagar
UP
1 Aug 201715 Aug 2023Overdue7 mo overdue
TOWN CENTRAL - PHASE-III
UPRERAPRJ7374
Gautam Buddha Nagar
UP
1 Aug 201715 Aug 2024In progressOn track