REGAL EMPORIA INFRATECH PRIVATE LIMITED
NAME:REGAL EMPORIA INFRATECH PRIVATE LIMITED
F0/100
Poor track record
Tracking 4 projects — 0 delivered, 4 still active. 4 of 4 (100%) ran late.
Delivery breakdown
How this builder's 4 tracked projects are split by outcome.
Key numbers
Total projects
4
Active
4
Completed
0
Delayed
4 (100%)
Late or overdue
Avg delay
—
On finished projects
On-time rate
—
Of completed projects
Extension rate
100%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (4)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| BOULEVARD WALK (PHASE 1) UPRERAPRJ7271 | Gautam Buddha Nagar UP | 4 Aug 2017 | 31 Mar 2020 | Overdue | 8 mo overdue |
| BOULEVARD WALK (PHASE 2) UPRERAPRJ7295 | Gautam Buddha Nagar UP | 10 Aug 2017 | 31 Jul 2021 | Overdue | 33 mo overdue |
| BOULEVARD WALK (PHASE 3) UPRERAPRJ7313 | Gautam Buddha Nagar UP | 10 Aug 2017 | 31 Jan 2022 | Overdue | 8 mo overdue |
| BOULEVARD WALK (PHASE 4) UPRERAPRJ15654 | Gautam Buddha Nagar UP | 10 Apr 2018 | 31 Dec 2020 | Overdue | 39 mo overdue |