PANCHSHEEL BUILDTECH PVT. LTD.
NAME:PANCHSHEEL BUILDTECH PVT. LTD.
F21/100
Poor track record
Tracking 12 projects — 11 delivered, 1 still active. 8 of 12 (67%) ran late by an average of 17 months.
Delivery breakdown
How this builder's 12 tracked projects are split by outcome.
Key numbers
Total projects
12
Active
1
Completed
11
Delayed
8 (67%)
Late or overdue
Avg delay
17.4 mo
Worst: 63 mo
On-time rate
36%
Of completed projects
Extension rate
58%
Projects with ≥1 extension
Complaints
0
On the registry
All projects (12)
Every registration we track for this builder. Click any project for the full timeline.
| Project | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|
| Panchsheel Greens UPRERAPRJ4386 | Gautam Buddha Nagar UP | 1 Aug 2017 | 1 Sept 2020 | Overdue | 70 mo overdue |
| PANCHSHEEL GREENS - II (TOWER-C1 TO C4,188 VILLAS) UPRERAPRJ8574 | UP | 12 Aug 2017 | 31 Mar 2019 | Completed | 8 mo delay |
| PANCHSHEEL GREENS - II (TOWER - D1,D2& E5) UPRERAPRJ8592 | UP | 12 Aug 2017 | 31 Aug 2021 | Completed | 63 mo delay |
| PANCHSHEEL GREENS - II (TOWER - E6,E7,D3 &D4) UPRERAPRJ8595 | UP | 12 Aug 2017 | 30 Nov 2022 | Completed | 48 mo delay |
| PANCHSHEEL HYNISH PHASE-2(TOWER- T10 & T11) UPRERAPRJ8538 | UP | 13 Aug 2017 | 1 Oct 2019 | Completed | On track |
| PANCHSHEEL HYNISH PHASE -3 (TOWER - T12) UPRERAPRJ8545 | UP | 13 Aug 2017 | 2 Jul 2020 | Completed | 6 mo delay |
| PANCHSHEEL GREENS-II(TOWER - E1 TO E4,COMMERCIAL,N UPRERAPRJ8584 | UP | 12 Aug 2017 | 31 Aug 2020 | Completed | 27 mo delay |
| PANCHSHEEL PINNACLE PHASE - 1 (TOWER - F2 & F3) PA UPRERAPRJ8845 | UP | 11 Aug 2017 | 31 Aug 2019 | Completed | 13 mo delay |
| PANCHSHEEL PINNACLE PHASE-2 (TOWER F1)PART OF PANC UPRERAPRJ8855 | UP | 11 Aug 2017 | 30 Nov 2020 | Completed | 27 mo delay |
| PANCHSHEEL HYNISH PHASE -1 (TOWER-T8 &T9) UPRERAPRJ8533 | UP | 13 Aug 2017 | 8 May 2018 | Completed | On track |
| PANCHSHEEL GREENS -II (TOWER - A1 TO A6,B1 TO B7) UPRERAPRJ8547 | UP | 12 Aug 2017 | 6 Jun 2018 | Completed | On track |
| PANCHSHEEL GREENS PHASE - 1 (B1 TO B3,F4 TO F6 & C UPRERAPRJ8832 | UP | 11 Aug 2017 | 30 May 2018 | Completed | On track |