Builders and projects in Thane · Maharashtra
Pick a state to narrow results, then search by builder, project, or RERA ID
Builders (50) · Thane
Open a builder to see their delivery grade and full track record.
Projects (50) · Thane
| Project | Builder | Location | Registered | Promised completion | Status | Delay |
|---|---|---|---|---|---|---|
| Konark Garden Phase IV P51700019886 | Konark NIrman Pvt. Ltd. | Thane MH | 11 Mar 2019 | 30 Nov 2020 | Completed | On track |
| VARDHMAN VATIKA P51700018906 | DIWALI DEVELOPERS | Thane MH | 11 Dec 2018 | 31 Dec 2019 | Completed | On track |
| Capsule Business Hub P51700015836 | Maa Vaishnavi Builders & Developers | Thane MH | 27 Mar 2018 | 30 Jun 2021 | In progress | On track |
| Naivaidya Heritage P51700014904 | Dilip Gangji Shah | Thane MH | 11 Jan 2018 | 1 Jan 2021 | Completed | On track |
| FENNEL G P51700013833 | ROYALE URBANSPACE LLP | Thane MH | 27 Oct 2017 | 30 Dec 2024 | In progress | On track |
| Rustomjee Azziano Wing K P51700013649 | Kapstone Constructions Private Limited | Thane MH | 16 Oct 2017 | 30 Sept 2022 | Completed | On track |
| Pandurang smruti P51700013381 | Lote Constructions | Thane MH | 4 Oct 2017 | 5 Jul 2019 | Completed | 12 mo delay |
| OM SAI SIDDHI P51700013347 | ASHTAVINAYAK ENTERPRISES | Thane MH | 22 Sept 2017 | 31 Dec 2019 | Completed | On track |
| DATTUSAI COMPLEX BUILDING NO 2 P51700013185 | SAIRAJ ENTERPRISES | Thane MH | 18 Sept 2017 | 31 Dec 2017 | Completed | On track |
| CELEBRATIONS P51800013187 | HINDUSTAN CONSTRUCTION CORPORATION | Thane MH | 18 Sept 2017 | 31 Dec 2017 | Overdue | 90 mo overdue |
| SAHAYOG NIWAS P51700013083 | SHREE DEVELOPERS | Thane MH | 14 Sept 2017 | 31 Jan 2020 | Completed | On track |
| vedant nakshatra ABC phase 1 P51700013039 | MOHAN HARDASMAL THARWANI | Thane MH | 14 Sept 2017 | 31 Dec 2017 | Completed | On track |
| HARISHREE RESIDENCY-1 P51700013029 | HARISHREE CREATIONS | Thane MH | 12 Sept 2017 | 30 Dec 2021 | Completed | On track |
| POONAM HEIGHTS P51700012649 | VIP REALTORS PRIVATE LIMITED | Thane MH | 7 Sept 2017 | 30 Dec 2023 | Overdue | 30 mo overdue |
| SHREYA APARTMENT P51700012665 | SHRADDHA SABURI DEVLOPERS | Thane MH | 7 Sept 2017 | 31 Dec 2017 | Overdue | 90 mo overdue |
| Sai Crystal P51700012359 | Shraddha Corporation | Thane MH | 1 Sept 2017 | 31 Dec 2017 | Completed | 4 mo delay |
| SPAN SIGNATURE P51700011940 | ANNAPURNA BUILDCON INFRA PVT LTD | Thane MH | 1 Sept 2017 | 30 Dec 2024 | Completed | On track |
| M/s. Shubham Karoti Complex Phase - II P51700012010 | M/s. Shubham Karoti Enterprises | Thane MH | 1 Sept 2017 | 31 Dec 2018 | Completed | On track |
| Hubtown Greenwoods - C Wing P51700012016 | Hubtown Limited | Thane MH | 1 Sept 2017 | 31 Jul 2018 | Completed | On track |
| MORYA RESIDENCY P51700012171 | SAIRATNA CONSTRUCTION | Thane MH | 1 Sept 2017 | 30 Sept 2020 | Completed | On track |
| SEASONS ELITE P51700012166 | SAI MAHAVIR DEVELOPERS | Thane MH | 1 Sept 2017 | 31 Aug 2019 | Completed | On track |
| KRISHNA RESIDENCY P51700012391 | KRISHNA ENTERPRISES | Thane MH | 1 Sept 2017 | 30 Nov 2018 | Completed | On track |
| KULSWAMINI PRASSANNA P51700012480 | KULSWAMINI DEVELOPERS | Thane MH | 1 Sept 2017 | 31 Aug 2019 | Completed | On track |
| DEVRAM SMRUTI P51700012446 | PATIL AND ASSOCIATES | Thane MH | 1 Sept 2017 | 30 Jun 2022 | Completed | On track |
| Vihang Plaza - A Commecial P51700012432 | VIHANG ENTERPRISES | Thane MH | 1 Sept 2017 | 30 Dec 2026 | In progress | On track |
| Shree Siddhivinayak Tower P51700012381 | Ekdant Constructions and Developers Private Limited | Thane MH | 1 Sept 2017 | 30 Dec 2020 | Completed | On track |
| SHAH SIGNATURE P51700012503 | SHAH GROUP BUILDERS & INFRAPROJECTS LTD | Thane MH | 1 Sept 2017 | 30 Dec 2021 | Overdue | 54 mo overdue |
| MIRADOR UTSAV PHASE 1 P51700012454 | Mirador Dewellers Pvt Ltd | Thane MH | 1 Sept 2017 | 30 Dec 2021 | Overdue | 6 mo overdue |
| WADHWA REGALIA PHASE III P51700011989 | WADHWA BUILDCON LLP | Thane MH | 1 Sept 2017 | 30 Dec 2023 | Overdue | 30 mo overdue |
| UTSAV P51700012319 | CLUBLIFE REALTORS PRIVATE LIMITED | Thane MH | 1 Sept 2017 | 15 Nov 2022 | In progress | On track |
| AL HADI RESIDENTIAL COMPLEX P51700012253 | SAHYADRI GRIH NIRMAN | Thane MH | 1 Sept 2017 | 30 Jun 2023 | Completed | On track |
| AMRUT PEARL BUILDING NO 1 P51700012040 | AMRUT BUILDERS | Thane MH | 1 Sept 2017 | 30 Dec 2022 | Completed | On track |
| USHA KIRAN RESIDENCY WING E1 E2 E3 P51700012135 | STALWART IMPEX PVT LTD | Thane MH | 1 Sept 2017 | 31 Dec 2017 | Completed | On track |
| AASARA CO-OP. HOUSING SOCIETY LTD. P51700012205 | SHREE SAIBABA GRIHANIRMITI PRIVATE LIMITED | Thane MH | 1 Sept 2017 | 31 Dec 2019 | Completed | 24 mo delay |
| Shreedham Excellency P51700012299 | Shreedham Construction Private Limited | Thane MH | 1 Sept 2017 | 30 Dec 2022 | Overdue | 42 mo overdue |
| KRISHNA PARADISE P51700012318 | GOPAL KRISHNA DEVELOPERS | Thane MH | 1 Sept 2017 | 30 Jun 2019 | Completed | On track |
| CHANDRANGAN RESIDENCY TYPE- A P51700012376 | EKVEERA ENTERPRISES | Thane MH | 1 Sept 2017 | 31 Dec 2019 | Completed | On track |
| Durahomes Builders and developers pvt ltd P51700012518 | Arshad Ahmed Siddiqui | Thane MH | 1 Sept 2017 | 31 Jul 2028 | In progress | On track |
| Venkatesh Heights P51700012201 | M/S Shree Balaji Foundation | Thane MH | 1 Sept 2017 | 31 Dec 2019 | Completed | 24 mo delay |
| Indrayani P51700012357 | Jangid Developers | Thane MH | 1 Sept 2017 | 30 Jun 2019 | Overdue | 18 mo overdue |
| GOLDCREST RESIDENCY - PHASE 1 P51700012365 | SAVITA HOMEMAKERS LLP | Thane MH | 1 Sept 2017 | 31 Dec 2019 | Completed | 12 mo delay |
| Rashmi Sarvesh P51700011990 | Rashmi Housing Private Limited | Thane MH | 1 Sept 2017 | 30 Jun 2023 | Overdue | 36 mo overdue |
| ANIRUDDHA LANDMARK P51700011992 | VASUDEV VISHWANATH PATIL | Thane MH | 1 Sept 2017 | 31 Mar 2019 | Completed | On track |
| SHANKAR PALACE P51700012469 | shree ramesh homes builders and developers | Thane MH | 1 Sept 2017 | 30 Oct 2023 | Completed | On track |
| VASTU SIDDHI P51700011663 | SIDDHIVINAYAK GROUP | Thane MH | 31 Aug 2017 | 30 Sept 2019 | Completed | On track |
| SAI RESIDENCY P51700011113 | KALPAVRUKSHA DEVELOPERS | Thane MH | 31 Aug 2017 | 31 Dec 2017 | Completed | 6 mo delay |
| Shree Ganesh Residency P51700011204 | Amol Padmakar Tarmale | Thane MH | 31 Aug 2017 | 31 Jan 2021 | Completed | On track |
| RAVIRAJ SPRING P51700011396 | M/s RAVIRAJ HOUSING (PRINCE CITY) | Thane MH | 31 Aug 2017 | 15 Dec 2018 | Completed | On track |
| SATIS CHS P51700010705 | PACIFIC IMPRESSION | Thane MH | 31 Aug 2017 | 31 Jan 2021 | Overdue | 39 mo overdue |
| Mangeshi Paradise - I P51700010709 | Annapurna Universal | Thane MH | 31 Aug 2017 | 31 Dec 2017 | Completed | On track |